RENDERING SAMPLES
All the following images display the rendering followed by its quality, timing, and description.
Very High Quality Rendering (1/5)
TOTAL TIME: 23 BUSINESS DAYS OR 4.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (10 days)
Rendering engine quality: High (5 days)
Post-production quality: High in Adobe Photoshop (4 days)
Changes: Moderate (3 days)
Very High Quality Rendering (2/5)
TOTAL TIME: 23 BUSINESS DAYS OR 4.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (10 days)
Rendering engine quality: High (5 days)
Post-production quality: High in Adobe Photoshop (4 days)
Changes: Moderate (3 days)
Very High Quality Rendering (3/5)
TOTAL TIME: 23 BUSINESS DAYS OR 4.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (10 days)
Rendering engine quality: High (5 days)
Post-production quality: High in Adobe Photoshop (4 days)
Changes: Moderate (3 days)
Very High Quality Rendering (4/5)
TOTAL TIME: 23 BUSINESS DAYS OR 4.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (10 days)
Rendering engine quality: High (5 days)
Post-production quality: High in Adobe Photoshop (4 days)
Changes: Moderate (3 days)
Very High Quality Rendering (5/5)
TOTAL TIME: 23 BUSINESS DAYS OR 4.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (10 days)
Rendering engine quality: High (5 days)
Post-production quality: High in Adobe Photoshop (4 days)
Changes: Moderate (3 days)
Medium High Quality Rendering (1/2)
TOTAL TIME: 8 BUSINESS DAYS OR 1.5 WEEKS
Number of renderings: 2 images
Starting method: Existing SketchUp 3D model (1 day)
Modeling quality: Medium (2 days)
Rendering engine quality: High (2 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: Minimal (1 day)
Medium High Quality Rendering (2/2)
TOTAL TIME: 8 BUSINESS DAYS OR 1.5 WEEKS
Number of renderings: 2 images
Starting method: Existing SketchUp 3D model (1 day)
Modeling quality: Medium (2 days)
Rendering engine quality: High (2 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: Minimal (1 day)
Very High Quality Rendering (1/2)
TOTAL TIME: 18 BUSINESS DAYS OR 3.5 WEEKS
Number of renderings: 2 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (6 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: Moderate (4 days)
Very High Quality Rendering (2/2)
TOTAL TIME: 18 BUSINESS DAYS OR 3.5 WEEKS
Number of renderings: 2 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (6 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: Moderate (4 days)
Medium High Quality Rendering (1/5)
TOTAL TIME: 20 BUSINESS DAYS OR 4 WEEKS
Number of renderings: 5 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: Medium (5 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
Medium High Quality Rendering (2/5)
TOTAL TIME: 20 BUSINESS DAYS OR 4 WEEKS
Number of renderings: 5 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: Medium (5 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
Medium High Quality Rendering (2/5)
TOTAL TIME: 20 BUSINESS DAYS OR 4 WEEKS
Number of renderings: 5 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: Medium (5 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
Medium High Quality Rendering (4/5)
TOTAL TIME: 20 BUSINESS DAYS OR 4 WEEKS
Number of renderings: 5 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: Medium (5 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
Medium High Quality Rendering (5/5)
TOTAL TIME: 20 BUSINESS DAYS OR 4 WEEKS
Number of renderings: 5 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: Medium (5 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
Very High Quality Rendering (1/6)
TOTAL TIME: 60 BUSINESS DAYS OR 12 WEEKS
Number of renderings: 6 images
Starting method: Existing CAD 2D drawings (2 days)
Modeling quality: High (30 days)
Rendering engine quality: High (10 days)
Post-production quality: High in Adobe Photoshop (8 days)
Changes: Frequent (10 days)
Very High Quality Rendering (2/6)
TOTAL TIME: 60 BUSINESS DAYS OR 12 WEEKS
Number of renderings: 6 images
Starting method: Existing CAD 2D drawings (2 days)
Modeling quality: High (30 days)
Rendering engine quality: High (10 days)
Post-production quality: High in Adobe Photoshop (8 days)
Changes: Frequent (10 days)
Very High Quality Rendering (3/6)
TOTAL TIME: 60 BUSINESS DAYS OR 12 WEEKS
Number of renderings: 6 images
Starting method: Existing CAD 2D drawings (2 days)
Modeling quality: High (30 days)
Rendering engine quality: High (10 days)
Post-production quality: High in Adobe Photoshop (8 days)
Changes: Frequent (10 days)
Very High Quality Rendering (4/6)
TOTAL TIME: 60 BUSINESS DAYS OR 12 WEEKS
Number of renderings: 6 images
Starting method: Existing CAD 2D drawings (2 days)
Modeling quality: High (30 days)
Rendering engine quality: High (10 days)
Post-production quality: High in Adobe Photoshop (8 days)
Changes: Frequent (10 days)
Very High Quality Rendering (5/6)
TOTAL TIME: 60 BUSINESS DAYS OR 12 WEEKS
Number of renderings: 6 images
Starting method: Existing CAD 2D drawings (2 days)
Modeling quality: High (30 days)
Rendering engine quality: High (10 days)
Post-production quality: High in Adobe Photoshop (8 days)
Changes: Frequent (10 days)
Very High Quality Rendering (6/6)
TOTAL TIME: 60 BUSINESS DAYS OR 12 WEEKS
Number of renderings: 6 images
Starting method: Existing CAD 2D drawings (2 days)
Modeling quality: High (30 days)
Rendering engine quality: High (10 days)
Post-production quality: High in Adobe Photoshop (8 days)
Changes: Frequent (10 days)
Medium Low Quality Rendering (1/1)
TOTAL TIME: 5 BUSINESS DAYS OR 1 WEEK
Number of renderings: 1 image
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: Low (1 day)
Rendering engine quality: Medium (1 day)
Post-production quality: High in Adobe Photoshop (1 day)
Changes: Minimal (2 days)
Low Quality Rendering (1/1)
TOTAL TIME: 4 BUSINESS DAYS OR ALMOST 1 WEEK
Number of renderings: 1 image
Starting method: None
Modeling quality: Low (2 days)
Rendering engine quality: Low (1 day)
Post-production quality: Low in Adobe Photoshop (1 day) and partially handdrawn.
Changes: None
Medium High Quality Rendering (1/2)
TOTAL TIME: 12 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 2 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (5 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (2 days)
Changes: None
Medium High Quality Rendering (2/2)
TOTAL TIME: 12 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 2 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (5 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (2 days)
Changes: None
High Quality Rendering (1/4)
TOTAL TIME: 16 BUSINESS DAYS OR ABOUT 3 WEEKS
Number of renderings: 4 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: Medium (4 days)
Rendering engine quality: High (4 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Moderate (4 days)
High Quality Rendering (2/4)
TOTAL TIME: 16 BUSINESS DAYS OR ABOUT 3 WEEKS
Number of renderings: 4 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: Medium (4 days)
Rendering engine quality: High (4 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Moderate (4 days)
High Quality Rendering (3/4)
TOTAL TIME: 16 BUSINESS DAYS OR ABOUT 3 WEEKS
Number of renderings: 4 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: Medium (4 days)
Rendering engine quality: High (4 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Moderate (4 days)
High Quality Rendering (4/4)
TOTAL TIME: 16 BUSINESS DAYS OR ABOUT 3 WEEKS
Number of renderings: 4 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: Medium (4 days)
Rendering engine quality: High (4 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Moderate (4 days)
High Quality Rendering (1/2)
TOTAL TIME: 16 BUSINESS DAYS OR ABOUT 3 WEEKS
Number of renderings: 2 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: High (4 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: None
High Quality Rendering (2/2)
TOTAL TIME: 16 BUSINESS DAYS OR ABOUT 3 WEEKS
Number of renderings: 2 images
Starting method: None
Modeling quality: High (10 days)
Rendering engine quality: High (4 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: None
Low Quality Rendering (1/2)
TOTAL TIME: 10 BUSINESS DAYS OR 2 WEEKS
Number of renderings: 2 images
Starting method: None
Modeling quality: High (5 days)
Rendering engine quality: None
Post-production quality: None
Changes: Frequent (5 days)
Low Quality Rendering (2/2)
TOTAL TIME: 10 BUSINESS DAYS OR 2 WEEKS
Number of renderings: 2 images
Starting method: None
Modeling quality: High (5 days)
Rendering engine quality: None
Post-production quality: None
Changes: Frequent (5 days)
Medium Low Quality Rendering (1/2)
TOTAL TIME: 9 BUSINESS DAYS OR ALMOST 2 WEEKS
Number of renderings: 2 images
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: Low (2 days)
Rendering engine quality: Medium (2 days)
Post-production quality: Medium (2 days)
Changes: Moderate (3 days)
Medium Low Quality Rendering (2/2)
TOTAL TIME: 9 BUSINESS DAYS OR ALMOST 2 WEEKS
Number of renderings: 2 images
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: Low (2 days)
Rendering engine quality: Medium (2 days)
Post-production quality: Medium (2 days)
Changes: Moderate (3 days)
High Quality Rendering (1/3)
TOTAL TIME: 12 BUSINESS DAYS OR ALMOST 2.5 WEEKS
Number of renderings: 3 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (4 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (1 day)
High Quality Rendering (2/3)
TOTAL TIME: 12 BUSINESS DAYS OR ALMOST 2.5 WEEKS
Number of renderings: 3 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (4 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (1 day)
High Quality Rendering (3/3)
TOTAL TIME: 12 BUSINESS DAYS OR ALMOST 2.5 WEEKS
Number of renderings: 3 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (4 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (1 day)
High Quality Rendering (1/2)
TOTAL TIME: 13 BUSINESS DAYS OR 2.5 WEEKS
Number of renderings: 2 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (4 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
High Quality Rendering (2/2)
TOTAL TIME: 13 BUSINESS DAYS OR 2.5 WEEKS
Number of renderings: 2 images
Starting method: Existing CAD 2D drawings (1 day)
Modeling quality: High (4 days)
Rendering engine quality: High (3 days)
Post-production quality: High in Adobe Photoshop (3 days)
Changes: Minimal (2 days)
Low Quality Rendering (1/2)
TOTAL TIME: 5 BUSINESS DAYS OR 1 WEEK
Number of renderings: 2 images
Starting method: None
Modeling quality: Low (2 days)
Rendering engine quality: Low (2 days)
Post-production quality: None
Changes: Minimal (1 day)
Low Quality Rendering (1/2)
TOTAL TIME: 5 BUSINESS DAYS OR 1 WEEK
Number of renderings: 2 images
Starting method: None
Modeling quality: Low (2 days)
Rendering engine quality: Low (2 days)
Post-production quality: None
Changes: Minimal (1 day)
Low Quality Rendering (1/1)
TOTAL TIME: 4 BUSINESS DAYS OR ALMOST 1 WEEK
Number of renderings: 1 image
Starting method: None
Modeling quality: Medium (3 days)
Rendering engine quality: None
Post-production quality: None
Changes: Minimal (1 day)
Medium Quality Rendering (1/2)
TOTAL TIME: 10 BUSINESS DAYS OR 2 WEEKS
Number of renderings: 2 images
Starting method: None
Modeling quality: High (4 days)
Rendering engine quality: Medium (3 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: Minimal (1 day)
Medium Quality Rendering (2/2)
TOTAL TIME: 10 BUSINESS DAYS OR 2 WEEKS
Number of renderings: 2 images
Starting method: None
Modeling quality: High (4 days)
Rendering engine quality: Medium (3 days)
Post-production quality: High in Adobe Photoshop (2 days)
Changes: Minimal (1 day)
Low Quality Rendering (1/1)
TOTAL TIME: 7 BUSINESS DAYS OR ALMOST 1.5 WEEKS
Number of renderings: 1 image
Starting method: Existing CAD 2D drawing (1 day)
Modeling quality: High (4 days)
Rendering engine quality: None
Post-production quality: None
Changes: Minimal (2 days)
Medium Quality Rendering (1/4)
TOTAL TIME: 12 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 4 images
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: None
Rendering engine quality: Medium (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Moderate (4 days)
Medium Quality Rendering (2/4)
TOTAL TIME: 12 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 4 images
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: None
Rendering engine quality: Medium (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Moderate (4 days)
Medium Quality Rendering (3/4)
TOTAL TIME: 12 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 4 images
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: None
Rendering engine quality: Medium (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Moderate (4 days)
Medium Quality Rendering (4/4)
TOTAL TIME: 12 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 4 images
Starting method: Existing SketchUp 3D model (0 days)
Modeling quality: None
Rendering engine quality: Medium (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Moderate (4 days)
Medium High Quality Rendering (1/5)
TOTAL TIME: 13 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawing (1 day)
Modeling quality: Medium (3 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Minimal (1 day)
Medium High Quality Rendering (2/5)
TOTAL TIME: 13 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawing (1 day)
Modeling quality: Medium (3 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Minimal (1 day)
Medium High Quality Rendering (3/5)
TOTAL TIME: 13 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawing (1 day)
Modeling quality: Medium (3 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Minimal (1 day)
Medium High Quality Rendering (4/5)
TOTAL TIME: 13 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawing (1 day)
Modeling quality: Medium (3 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Minimal (1 day)
Medium High Quality Rendering (5/5)
TOTAL TIME: 13 BUSINESS DAYS OR ABOUT 2.5 WEEKS
Number of renderings: 5 images
Starting method: Existing CAD 2D drawing (1 day)
Modeling quality: Medium (3 days)
Rendering engine quality: High (4 days)
Post-production quality: Medium in Adobe Photoshop (4 days)
Changes: Minimal (1 day)